Trans Nzoia County Investments
47 CCRIG-financed projects in Trans Nzoia County, with a combined value of KSh 184,179,260.
| Project Name | Sector | Project Cost | Ward | Status |
|---|---|---|---|---|
| Kiboroa-Saboti-Chemichemi water supply project | Water | KSh 15,000,000 | Saboti and Machewa | Pending |
| Kiminini-Nabiswa water supply project | Water | KSh 15,000,000 | Kiminini and Nabiswa | On track |
| Promotion of apiculture for improved livelihood and environmental conservation project in Kaplamai ward | Agriculture | KSh 11,775,920 | Kaplamai, Makutano, Endebess | Pending |
| Promotion of climate smart agroforestry tree species project | Environment | KSh 11,000,000 | Endebess, Chepchoina, Keiyo, makutano, Sikhendu | Pending |
| Integration of fruit trees in the farming system | Agriculture | KSh 8,375,000 | Matumbei, Endebess | Pending |
| Bondeni-Chalicha water supply project | Water | KSh 7,000,000 | Machewa ward: Water intake Rehabilitation of the storage tank Sikhendu ward: Downstream tanks 1 Downstream tanks 2 Downstream tanks 3 Downstream tanks 4 Rehabilitation of the Storage Tank 100m3 | Pending |
| Karara dam rehabilitation | Water | KSh 7,000,000 | Kaplamai | On track |
| Lumuli dam rehabilitation Project | Water | KSh 7,000,000 | Sirende | Pending |
| Nasianda-Teldet water supply project | Water | KSh 7,000,000 | Kinyoro | Pending |
| Robinson dam Rehabilitation | Water | KSh 7,000,000 | Chepchoina | Pending |
| Kitum-Sendera water supply project | Water | KSh 6,000,000 | Endebess | Pending |
| Rehabilitation of the river sabwani riparian area | Environment | KSh 5,530,000 | Sitatunga | Pending |
| Establishment of climate smart forage multiplication/bulking site project | Agriculture | KSh 5,000,000 | Chepsiro, Kiptoror Makutano Waitaluk Kiminini Hospital Kapomboi Kapsitwet Kinyoro Machewa Matumbei | Pending |
| Establishment of livestock fodder production site | Agriculture | KSh 5,000,000 | Chepsiro, Kiptoror Makutano Waitaluk Kiminini Hospital Kapomboi Kapasitet Kinyoro Machewa Matumbei | Pending |
| Masaba water supply project | Water | KSh 5,000,000 | Matumbei | Pending |
| Promotion of aquaculture for improved livelihood and environmental conservation project in Sitatunga ward | Agriculture | KSh 5,000,000 | Sitatunga Sinyereri Keiyo Kaplamai, Waitaluk, Chepchoina | Pending |
| Wamuini dam rehabilitation, pipeline extension project | Water | KSh 5,000,000 | Waitaluk | Pending |
| Kapchemakwer-Makutano water gravity scheme project | Water | KSh 3,300,000 | Makutano | Pending |
| County Tree Nursery borehole equipping | Water | KSh 3,000,000 | Bidii | Pending |
| Keiyo farm ponds construction project | Agriculture | KSh 3,000,000 | Keiyo | Pending |
| Establishment of improved jiko/stove liner Production Center | Green energy | KSh 2,648,900 | Matisi, Waitaluk | Pending |
| Bwake Borehole Equipping Project | Water | KSh 2,500,000 | Makutano | Completed |
| Kaisagat borehole equipping | Water | KSh 2,500,000 | Kwanza | Pending |
| Kapcheplanget tank construction | Water | KSh 2,500,000 | Chepsiror, Kiptoror | Pending |
| Kudos borehole equipping | Water | KSh 2,500,000 | Matumbei | Pending |
| Kwa wena borehole equipping | Water | KSh 2,500,000 | Nabiswa | Pending |
| Sinoko borehole equipping | Water | KSh 2,500,000 | Motosiet | On track |
| St. Peter Mucharage borehole equipping | Water | KSh 2,500,000 | Sikhendu | On track |
| St. Thomas borehole equipping | Water | KSh 2,500,000 | Motosiet | Off track |
| Promotion of climate smart early maturing crops in Hospital ward | Agriculture | KSh 2,250,000 | Hospital | Pending |
| Promotion of climate smart early maturing crops in Hospital ward | Agriculture | KSh 2,250,000 | Bidii | Pending |
| Promotion of climate smart early maturing crops in Hospital ward | Agriculture | KSh 2,250,000 | Sirende; Makutano; | Pending |
| Establishment of Briquettes Production Center | Green energy | KSh 2,000,000 | Bidii | Pending |
| Kwanza public schools Roof catchment project | Environment | KSh 2,000,000 | Kwanza | Pending |
| Tuwan public schools Roof catchment project | Environment | KSh 2,000,000 | Tuwan | Pending |
| Establishment of Community tree nurseries | Environment | KSh 1,549,440 | Endebess; Waitaluk, Matisi | Pending |
| Endebess market pipeline extension | Water | KSh 1,500,000 | Endebess | Pending |
| Shimo la Tewa and Spring Valley springs protection | Water | KSh 1,000,000 | Hospital | Pending |
| Promotion of climate smart crop production technology | Agriculture | KSh 500,000 | Waitaluk Sikhendu & Hospital | Pending |
| Sinoko Dispensary | Infrastructure | KSh 500,000 | Motosiet | Pending |
| Baraka spring protection | Water | KSh 250,000 | Sirende | Pending |
| Cherubai springs protection | Water | KSh 250,000 | Chepchoina | Pending |
| Kaptaragon spring protection | Water | KSh 250,000 | Chepsiro, Kiptoror | Pending |
| Mengo spring protection | Water | KSh 250,000 | Saboti | Pending |
| Munyasi spring protection | Water | KSh 250,000 | Sinyereri | Pending |
| Murembe spring protection | Water | KSh 250,000 | Kwanza | Off track |
| Nabutola spring protection | Water | KSh 250,000 | Sirende | Pending |